Research Article

CONTRACTOR SELECTION MODEL IN COMPETITIVE BIDDING SYSTEM

1 Department of Quantity Surveying, Faculty of Environmental Sciences, Bingham University, Abuja-Keffi Expressway, Nasarawa State Nigeria
2 Department of Quantity Surveying, Faculty of Environmental Sciences, Kaduna State University, Kafanchan Campus
* Corresponding author: yusufgandu@yahoo.com
Published: Dec, 2021
Pages: 105-115
Views: 49
Downloads: 22

Abstract

The lowest bid has often been favoured for award of contracts in competitive bidding. Despitethe fact that the essence is to achieve value for money for the client, studies show that the lowestbid doesn't often guarantee cost efficacy of construction projects. Different models have beendeveloped to improve on the lowest bid award system. Some of the research results producedregression models that will identify not just any lowest bid but the lowest responsive responsiblebid among bidders. However, the independent variables in such equations raise some questionsthat demand answers from research consideration. The major questions were the rational onthe choice of variables and the reasons for using only two independent variables in theequations. This research is set to consider those questions in developing a more reliableregression model that will identify the lowest responsive responsible bid in competitive bidding.Water engineering projects competed in the north eastern part of Nigeria between 2015 and2017 were used. Thirty six (36) completed projects of diverse magnitudes involving 220 bidswith diverse level of competition were used. Three new regression models were developed, twoof which has 3 independent variables and one has 4 intendant variables. Both were comparedwith earlier similar equations developed with 2 independent variables. It was found thatdifferent matrixes of independent variables presented different predictive power of the lowestresponsive responsible bid. Comparison shows that the equation with 4 independent variablesis the most robust predictor of the lowest responsive responsible bid. However, for the sake ofconvenience and early identification, the optimum equation with 2 variables containing thenumber of bids and the consultant's estimate was recommended. This is in line and justifiesearlier research recommendations. It is expected that the result will enable quick identificationof bon-a'-fide contractor at the early stage of the bidding process through which thecumbersome task of bid analyses will be reduced, as such cost and time of bidding also reduced.

References

  1. Aje, I. O., Oladinrin, T. O. & Nwaole, A. N. C. (2016). Factors influencing success rate of contractors in competitive bidding for construction works in South-East, Nigeria. Journal of Construction in Developing Countries, 21(1), 19–34. Available online on [http://dx.doi.org/10.21315/jcdc2016.21.1.2](https://www.google.com/search?q=http://dx.doi.org/10.21315/jcdc2016.21.1.2)
  2. Alumbugu, P. O., Ola-Owo, W. A., Saidu, I., Abdullahi, M. M. & Abdulazeez, A. (2014). Assessment of the factors affecting accuracy of pre-tender cost estimate in Kaduna State, Nigeria. IOSR Journal of Environmental Science, Toxicology and Food Technology (IOSR-JESTFT), 8(5):19-27. Available online on www.iosrjournals.org.
  3. Azeez, R. M. & Aboelmagd, Y. M. (2019). Integration between different construction bidding models to improve profitability and reduce prices. Alexandria Engineering Journal, 58(1):151-162. Available online on [www.elsevier.com/locate/aej](https://www.google.com/search?q=https%3A%2F%2Fwww.elsevier.com%2Flocate%2Faej).
  4. Bajaber, M. A. & Taha, M. A. (2012). Contractor Selection in Saudi Arabia. International Scholarly and Scientific Research and Innovation,6(11):2995-3000. Available online on 2995 www.scholar.waset.org/1307-6892/14292.
  5. Bruik, S., Jaskowski, P. & Czarnigowska, J. A. (2017). Modelling contractor's bidding decisions.ProcediaEngineering, 182 (2017) 91-98. The 7th International Conference on Engineering, Project, and Production Management. doi:10.1016/j.proeng.2017.03.125.
  6. Carr, P.G. (2005). Investigation of bid price competition measured through pre-bid project estimates, actual bid prices, and number of bidders.Journal of Construction Engineering and Management, 131(11): 1165.
  7. Cunningham, T. (2017) Cost Control during The Construction Phase of the Building Project: - The Consultant Quantity Surveyor's Perspective, Dublin Institute of Technology.
  8. Gandu, Y. J., Isah S. I. & Chindo, P. G. (2020). Early identification of lowest responsive bid in competitive bidding process of construction projects. American Journal of Engineering Research (AJER), Volume-9, Issue-1, pp-138-146, www.ajer.org. USA, e-ISSN: 2320-0847 p-ISSN: 2320-0936.
  9. Hafez, S. M., Aziz, R. F. and Elzebak, H. M. M. (2015). Optimal Techniques for Cost Reduction and Control in Construction Sites. Journal of Human Resource Management, 3(3):17-26. doi:10.11648/j.jhrm.20150303.11.
  10. Hiyassat, M. A. (2000). Construction Bid Price Evaluation. Canadian Journal of Civil Engineering, 28(2000):264–270.
  11. Khan, T. H. and Khan, A. Q. (2015). Effects of Lowest Bidding Bid Awarding System In Public Sector Construction Projects In Pakistan. Developing Country Studies, 5(3):132-147. www.iiste.org.
  12. Kim, Y. J. & Skibniewski, M. J. (2020). Unsuccessful bids: Coefficient of variation of bids as indicator of project risk. Sciendo. Organization, Technology and Management in Construction, 2020(11): 2193–2199. DOI 10.2478/otmcj-2020-0015.
  13. Kumar, J. K. & Raj, S.V. (2020). Bid decision model for construction projects-A review. Materials Today: Proceedings, 22(2020):688–690. Available online at [https://doi.org/10.1016/j.matpr.2019.09.144](https://www.google.com/search?q=https://doi.org/10.1016/j.matpr.2019.09.144).
  14. Mahmood, S., Shahrukh and Sajid, A. (2010). Impact of lowest bid procurement syndrome on quality: case study of public sector in developing nations. Paper presented at 13th QMOD conference on Quality and Service Sciences ICQSS 2010, August 30 - Sep.01, 2010 Hosted by Brandenburg University of Technology, Cottbus Germany.
  15. OECD (Organisation for Economic Co-Operation and Development, 2011). Competition and Procurement. Available online at www.oecd.org/competition/roundtables.
  16. Oladokun, M. G., Oladokun, A. A. and Odesola, I. A. (2010). Accuracy of Pre-Tender Cost Estimates of Consultant Quantity Surveyors in Nigeria. Journal of International Real Estate and Construction Studies 1(1):39-51
  17. Oyeyipo, O. O., Odusami, K. T.,Ojelabi, R. A. and Afolabi, A. O. (2016). Factors Affecting Contractors' Bidding Decisions for Construction Projects in Nigeria.Journal of Construction in Developing Countries, 21(2), 21–35. Available online on [https://dx.doi.org/10.21315/jcdc2016.21.2.2](https://www.google.com/search?q=https://dx.doi.org/10.21315/jcdc2016.21.2.2)
  18. Prajapati, R., Pitroda, J. and Bhavasar, J. J. (2015). Analysis of factor affecting contractor's bidding strategy using RII method. International Journal of Modern Trends in Engineering and Research (IJMTER), 02(04):2349–9745.
  19. Puri, D. & Tiwari, S. (2014). Evaluating The Criteria for Contractors' Selection and Bid Evaluation. International Journal of Engineering Science Invention, 3(7):44-49. Available online on www.ijesi.org.
  20. Sammoura, R, (2010). A Simulation Model for Bid Price Decision Making. World Academy of Science, Engineering and Technology. International Journal of Economics and Management Engineering, 4(5):529532. Fromscholar.waset.org/13076892/14070
  21. Shrestha, P. P. and Pradhananga, N. (2010). Correlating Bid Price with the Number of Bidders and Final Construction Cost of Public Street Projects. Journal of the Transportation Research Board. DOI: 10.3141/2151-01.
  22. Zavadskas, E. K., Turskis, Z. & Tamosaitiene, J. (2008). Contractor selection of construction in a competitive environment. Journal of Business Economics and Management, 9(3): 181–187. DOI: 10.3846/1611-1699.2008.9.181-187
How to Cite

Gandu, Y. J., & Zaki, Y. M. (2021). CONTRACTOR SELECTION MODEL IN COMPETITIVE BIDDING SYSTEM. Kaduna State University Environmental Sciences Journal, 2(2), 105-115. https://doi.org/10.66884/kesj.2021.pbgx3v8s

Y. J. Gandu, and Y. M. Zaki, "CONTRACTOR SELECTION MODEL IN COMPETITIVE BIDDING SYSTEM," Kaduna State University Environmental Sciences Journal, vol. 2, no. 2, pp. 105-115, December 2021. doi: 10.66884/kesj.2021.pbgx3v8s

Share this article:
Facebook X / Twitter LinkedIn